Inspection Core Principle

  • Dual-dimension Verification : Qualification inspection needs to cover two dimensions of electrical performance (continuity/insulation) and mechanical connection (fixation/stability) to ensure reliable operation of the connector.

Two-step Quick Inspection Process

① Electrical Performance Test

After wiring, test continuity and insulation with a multimeter: insulation resistance between cores, and between core and shell ≥100MΩ@500V DC, no short circuit between any cores.

② Mechanical Connection Test

Tighten the nut after mating, pull the cable lightly without falling off; shake the connector and the multimeter reading has no jump, indicating good contact and stable connection.